At KSC, an $800 million center was built to accommodate this new rocket—Launch Complex 39. It included a hangar to hold four Saturn V rockets, the Vehicle Assembly Building (VAB, 130 million ft³); a transportation system from the hangar to the launch pad, capable of carrying 5440 tons; a 446-foot (136 m) movable service structure and a control center. Construction began in November 1962, the launch pads were completed by October 1965, ...
more
Also known as:
- At KSC, an $800 million center was built to accommodate this new rocket—Launch Complex 39. It included a hangar to hold four Saturn V rockets, the Vehicle Assembly Building (VAB, 130 million ft³); a transportation system from the hangar to the launch pad, capable of carrying 5440 tons; a 446-foot (136 m) movable service structure and a control center. Construction began in November 1962, the launch pads were completed by October 1965, the VAB was completed in June 1965, and the infrastructure by late 1966. From 1967 through 1973, there were 13 Saturn V launches from Complex 39.